City of Bedford, Indiana


NEWS & HAPPENINGS

BUILDING A BETTER BEDFORD WEEKLY UPDATE-AUGUST 10, 2018

BUILDING A BETTER BEDFORD WEEKLY UPDATE-AUGUST 10, 2018

August 10, 2018

BUILDING A BETTER BEDFORD WEEKLY UPDATE, AUGUST 10TH, 2018 STELLAR STREETSCAPE, LIMESTONE TRAIL CONNECTOR, AND FACADE RENOVATION PROJECTS Contact: Marla Jones Dan Kirk Director of Business & Community Development Street Commissioner (812) 275-1601 (812) 275-1631 mjones@bedford.in.us dkirk@bedford.in.us www.mybedfordonline.in.us STELLAR DOWNTOWN STREETSCAPE PROJECT Construction is underway to update the streetscape in downtown Bedford. Below is a list of activities that we anticipate happening over the next week. A weekly update will be distributed during the remainder of the streetscape construction. NOTE: New work hours are Mon thru Fri 6:30 AM to 3:00 PM. No work on Saturdays. Last week’s progress: • 15th Street (West Half): o Continued backfilling behind edge treatment walls and at Masonic Temple basement. o TC Electric installed light pole foundations and ran wiring. • 16th Street (East Half): o Edge Treatment walls completed except for the Limestone Caps which will be installed after all sidewalk and steps are poured. o Sidewalk pouring operations continued (85% complete). o Pour the curb ramp at the southwest corner of 16th Street and I Street. • 16th Street (West Half) & 15th Street (East Half): o Duke Energy has been notified that they can begin installing new light pole foundation. Installation date is to be determined pending Duke Energy schedule. o Temporary Handrail in place until new handrail is on site and installed. • 15th Street and J Street (Northeast corner of intersection): o Removals are complete. o Fire Hydrant has been relocated. o TC Electric installing foundations and pulling wire for Pedestrian signals. What to expect August 13th thru August 18th: • 15th Street (West Half): o Continue backfilling edge treatment walls. o Begin setting grade and prep for sidewalk pours. Contractor will first pour sidewalk along the building faces prior to constructing sidewalk and curb along the road. • 16th Street (East Half): o Finish pouring sidewalk, ramps and curb. o Begin installing Limestone Caps on the Edge Treatment walls. NOTE: Weather could affect some work activities and could cause delays. Customer Access: • On the south side of 16th Street from J Street to I Street: o Pedestrian access via the ramp at 16th Street and J Street has been restored. o Some stairs remain closed for public safety, due to a lack of handrail. o Access to all business can be obtained via the new sidewalk in front of the Courthouse Annex or via 16th Street and J Street. • On the north side of 15th St from J Street to I Street: o Access to businesses on the east half of the block from I Street to the Masonic Temple can be obtained via new concrete sidewalk. Access is obtained off of I Street. o Businesses west of the Masonic Temple can be accessed via individual walkways in front of the business. Parking/Traffic: • There will be no parking on the east half of 16th Street during construction of the east half of the block. • There will be no parking on the west half of 15th Street during construction of the west half of the block. • Eastbound US 50 (16th Street) and Westbound US 50 (15th Street) – The right lane will be closed from 7:00 AM to 4:30 PM - MONDAY thru SATURDAY during construction. • For 16th Street the lane closure configuration will start immediately west of J Street and continue through to the middle of the block between I Street and J Street. • For 15th Street the lane closure configuration will start immediately east of I Street and continue through to the middle of the block between I Street and J Street. NOTE: (HANDRAIL STATUS) • Cost quotes have been finalized and all drawings have been approved. Approval has been obtained to move forward with a change order to add decorative handrail to the contract. STELLAR LIMESTONE TRAIL CONNECTOR PROJECT Construction is underway on the Limestone Connector, connecting the Milwaukee Trail at 10th Street to the Downtown Streetscape & Courthouse Square via Lincoln Avenue/L Street, 14th Street & 17th Street. Below is a list of activities that we anticipate happening over the next week. A weekly update will be distributed during the remainder of the Limestone Trail construction. NOTE: Work hours are 7:00 AM to 5:00 PM Monday – Saturday. Last week’s progress: • Finished pouring sidewalk/Trail and drive approaches on Lincoln Avenue from 13th Street towards 14th Street. • Began pouring curb and sidewalk/Trail on 17th Street from J Street towards K Street. • Began installing sod and planter beds on Lincoln Avenue and L Street from 10th Street to 13th Street. o NOTE: Sod will be watered by contractor every day for 30 days excluding Sundays. Sod was installed on 26 July 2018. Please do not mow the newly placed sod for 30 days from the date of placement due to warranty obligation on the contractor for sod maintenance. • Finished placing asphalt on Lincoln Avenue and L Street from 10th Street to 14th Street as well as on 14th Street from K Street to L Street. • Began reconstructing Limestone Wall on Lincoln Avenue just south of 10th Street. • Began removals along L Street from 14th Street to L Street. • Set up lane closure on L Street from 16th Street to 14th Street. Traffic configuration in said: Southbound Lane Closed, Northbound one way only is open. • Began installing post foundations for bike rail on Lincoln Avenue just south of 10th Street. What to expect the week of August 13th thru August 18th: • Finish placing planter beds and dirt behind curbs on L Street from 13th Street to 14th Street. • Finish removal on L Street from 16th Street to 14th Street. • Begin installing new storm sewer on L Street starting at 16th Street working towards 15th Street. • Continue pouring sidewalk, curb and rives on 17th Street from J Street towards K Street. NOTE: Weather could affect and delay construction activities. Customer Access: • The new sidewalk on the south side of 14th Street is open to pedestrians. • The sidewalk on the north side of 17th Street is closed from J Street to K Street. The contractor has maintained access to thru foot traffic along the south side of 17th Street. • The sidewalk on the west side of Lincoln Avenue from 10th Street to 14th Street is closed. Pedestrian access will be maintained via the sidewalk on the east side of Lincoln Avenue from 10th Street to 14th Street. Parking/Traffic: • Lincoln Avenue and L Street is open to northbound and southbound traffic from the Round-a-bout to 14th Street. • L Street from 14th Street to 16th Street will be one way north only for approx 45 days beginning 30 July 2018 (Monday). • 17th Street from J Street to K Street: The westbound lane is closed. One way eastbound traffic only is open. STELLAR FAÇADE RENOVATION PROJECT Construction is underway for the Stellar Community Facades Renovation Project. Below is a list of activities we anticipate happening next week. A weekly update will be distributed during the remainder of the Façades Renovation construction project. Last Week’s Progress- August 2nd thru August 9th: • Finished EIFS at 1537 J Street • Worked on clock at 1501 J Street • Started scaffolding and EIFS at 1011 15th Street What to expect the week of August 10th thru August 17th • Continue EIFS at 1011 15th Street • Finish break metal on 1016 16th Street • Start storefront doors at 1011 15th Street • Start tuck-pointing at 1509 J Street • Start new entry at 1509 J Street If you would like to be added to the Building A Better Bedford Weekly Updates list serve, please send your email address to Debbi Andry at dandry@bedford.in.us.

CITY OF BEDFORD COUNCIL MEETING

CITY OF BEDFORD COUNCIL MEETING

August 01, 2018

The Bedford City Council Meeting Will Be Held On Tuesday, August 14th at 7:00 PM In The City Hall Mark E. Scherschel Sr. Council Chambers.

Redevelopment Commission Meeting

Redevelopment Commission Meeting

August 01, 2018

The Bedford Redevelopment Commission Will Hold Their Meeting On Monday, August 13th At 4:00 PM In The City Hall Mark E. Scherschel Sr. Council Chambers.

City of Bedford Board of Works and Safety

City of Bedford Board of Works and Safety

August 01, 2018

The Board of Works And Safety Will Hold Their Regular Meeting On Monday, August 20th At 4:00 PM In The City Hall Mark E. Scherschel Sr. Council Chambers.

CITY OFFICES CLOSED - LABOR DAY

CITY OFFICES CLOSED - LABOR DAY

August 01, 2018

NOTICE: All Bedford City Offices will be closed on Monday, September 3rd, 2018 in observance of Labor Day. TASC BUSES WILL NOT BE RUNNING. Monday’s trash pickup will be Saturday, September 1st. Compost pick up will be Tuesday, September 4th.

UPDATE: John Williams Blvd / Lincoln Ave Roundabout

UPDATE: John Williams Blvd / Lincoln Ave Roundabout

July 26, 2018

Please view our video on the John Williams Blvd / Lincoln Ave. Roundabout. https://www.youtube.com/embed/lVelku4JqlQ

Login to your Emergency Alerts Profile (Must register first)

Login to your Emergency Alerts Profile (Must register first)

July 20, 2018

View and update your profile

Road Closure 10th & O St to begin 7/30 6 AM

Road Closure 10th & O St to begin 7/30 6 AM

July 20, 2018

10th & O Street will be closed beginning Monday 7/30 at 6 am. except for local traffic. You will not be able to exit onto O St going south from JWB. Please use R street as the detour from JWB. You will not be able to go under the trestle on O St going north. Love On A Leash dog grooming customers need to use M Street and turn left on 10th St. Lincoln Avenue at the round about will be open on Wednesday August 1 and Lincoln Ave and R St can be used until 10th and O will be open again. A sanitary sewer is being replaced and the contractor is ready to cross under the trestle and go North on O St. We apologize for this inconvenience but this closure is necessary for the safety of the public and the workers.

Register for Emergency Alerts

Register for Emergency Alerts

July 19, 2018

Register for Emergency Alerts for the City of Bedford

More News

EVENTS

03 Sep 2018

Bedford City Offices Closed-Labor Day

NOTICE: All Bedford City Offices will be closed on Monday, September 3rd, 2018 in observance of Labor Day. TASC BUSES WILL NOT BE RUNNING. Monday’s trash pickup will be Saturday, September 1st. Compost pick up will be Tuesday, September 4th.

31 Oct 2018

Halloween Trick or Treat

The City of Bedford will hold its Halloween Trick or Treat Night on Wednesday, October 31st from 6:00 - 9:00 PM. - ONE NIGHT ONLY!

More Events

Featured Sites

No data to display