City of Bedford, Indiana



BUILDING A BETTER BEDFORD - PRESS RELEASE - ROAD PAVING
Friday, July 26, 2019


 PRESS RELEASE - ROAD PAVING

The City of Bedford will begin paving all the City Streets in the Edgewood Addition starting on Tues July 30th 2019.

Milling on the roads will begin for the first three Days. (Tues, Weds, and Thurs).  On Friday, August 2nd, paving will begin and is scheduled as followed:

Friday August 2nd…………..Windwood and Linwood Drive

Monday August 5th……….Jay Hunter Drive, Circle Court and Woodhill Drive

Tuesday August 6th……….Circle Drive, Central Avenue and Grimes Street

Wednesday August 7th…Northwood and Eastwood Drives

Thursday August 8th……..Southwood and Westwood Drives

Friday August 9th………….Edgewood Drive

As always this is a tentative schedule subject to change due to weather and unforeseen circumstances.

Dan Kirk

Planning and Zoning Director

Street Commissioner

City Of Bedford

1102 16th street

Bedford In 47421

812-275-1632

FAX 812-275-1659

E-Mail dkirk@bedford.in.us